Saturday, March 6, 2010

TM Report: Mianus River Park

Date of Activity: 3/6/10
Condition of Trails(s): Muddy in spots

Trail Ambassador Name: David Francefort, Ryan Tucker, Kyaiera Tucker, Rich Coffee
Trail Ambassador Email: dfrancefort@excite.com

Town: Stamford
Location: Mianus River Park
Trail(s) Ridden: N/A
How did you use the trail?: Trail Maintenance
What was the time of day?:9:00AM
Duration (Hours): 4
Distance (Miles): N/A

Observations: Great turnout today 4 TA's and 5 other workers. Project 1 (second Loop trail): Installed knick, de-burmed downward slope side of trail, armored 20 foot section and added an aqueduct across the trail, lined with stone to accept over flow from an adjacent vernal pool, cleared an existing channel of leaves.

Project 2 (second Loop trail): Armored a 30 foot section of trail that is always muddy, which included bringing down some very large boulders from the hillside. As we where completing the armoring project our first ride came along and rode the new armor giving the thumbs up.